Manning Field Project Near Finish Line
LYNN - The long awaited completion
of Manning Field, the successor to Manning Bowl, which was demolished in 2005,
is reportedly right around the corner.
Although it was originally slated to be finished in May, Inspectional Services
Director Michael Donovan said the completion date is now set for July 1.
"It's really coming along, and we're pretty much all done," he said.
"We just have to install the aluminum windows and do the final painting on
the press box."
Donovan said minor theft of the bleachers occurred and the city had to purchase
more materials to complete the seats.
"Some of the aluminum and galvanized steel went missing, and it wasn't
enough to even report to the police," he said. "We also had some
missing from the factory."
In regards to spending, Donovan said it was a struggle, but the city remained on
track.
Funding for the project included $4.18 million in bonds from the city; a state
grant of $5 million; a Brownfields grant of $70,000; a state Brownfields earmark
of $200,000; a self-help grant from the state for $500,000; $680,000 from the
sale of the Joseph Devlin Nursing Home and other small amounts totaling
$250,000, according to Donovan.
Quirk Construction of Georgetown installed lighting and laid down the track and
field at a cost of $3.2 million for the first phase of the project.
J & J Contractors handled the second phase of the project, which included
the installation of over 4,000 bleacher seats, a field house, locker room,
concession stand, restrooms, office space and a press box.
Donovan said the city is handling the third phase of the project, which includes
a multitude of minor tasks such as wiring for telephones, and installing the
public announcement system.
"There is a track meet scheduled at the field in the next couple of weeks
and everything will officially be open for the football season in the
fall," he said. "All the big stuff is done, and we're ready to push
the ball over the goal line."
The field is located behind Fraser Field and borders Western Avenue, Locust and
Ford streets.
![]() |
| Construction on the Manning Field building is progressing, and workers are expected to begin installing permanent bleachers soon. (ITEM PHOTO / OWEN O'ROURKE) |
Manning Field Building Construction is Progressing
The Manning Field building project is starting to come
together and with some cooperation from Mother Nature and no surprises on any
other fronts, the structure should be substantially completed sometime between
mid-April and mid-May.
Community Development's John Kasian said the spring sports teams will have use
of the field and the track and the permanent stands will be in place on the
Locust Street side. He said the portable bathrooms would still be necessary, at
least for the first few weeks of the season. The spring sports season begins
Monday, March 17, which is the first official day of practice. The first
scheduled league lacrosse game at the field will be March 31.
At this point, the building is actually two separate structures with three-story
shafts on each. Once the building is complete, the two buildings will be
connected at the third floor level by a press box. According to Kasian, there
will also be a trestle connecting the two buildings at the second-floor level.
Those who need handicapped access will be able to reach the lower level of the
stands using ramps and the upper level (on the parking lot side of the field)
using the elevator, which will be located in the shaft on the Ford Street side.
Anyone driving down Locust Street these days would see the shaft sections of
both buildings shrouded by tarps that allow the construction people to complete
the masonry work somewhat protected from the elements.
"You can see it's really moving along," Kasian said about the building
progress.
Although the parking lot won't be paved under the current phase of the job, it
will be usable when the North Shore Navigators, the new baseball team that will
call Fraser Field home this summer, start their season in early June, Kasian
said.
Kasian said the Navigators and the visiting team will be allowed to use the team
rooms on the first floor of the new building. That level will also include a
concession stand, office and bathrooms. There will be more bathrooms on the
second floor as well and the press box will be on the third floor.
Although there will be shower facilities for the officials, there are none in
the team rooms, Kasian said.
Kasian said the stands on the parking lot side of the field, in front of the
building, will go up after the stands on the Locust Street side. The overall
project will also include a prefabricated storage building, but that won't be
done until after the spring season.
---------------------------
Manning Field Ready to Spring into Action
---------------------------------------
Manning Field Construction
Moving Along
By Jill Casey, The Daily Item of Lynn, Thursday,
June 1, 2006
LYNN - Despite record
rainfall last month, Phase 1 of the Manning Field construction project is only a
few days behind and will be ready for football season in the fall, according to
Inspectional Services Director Michael Donovan.
Because setbacks are built into the contract, the
2-3 days lost during the week of the floods is not considered a major delay,
according to Donovan.
"The contractor has not indicated that he is
behind," Donovan said. "Essentially, we're fairly on track for
mid-September."
Work began on April 13 and officials anticipate
contractors with Quirk Construction of Georgetown will install the track in
July, and the playing surface in August.
Although contractors will still be working in
October, finishing landscaping and fence work, local football teams will be
playing on the new field in September.
Donovan said with the exception of wet weather,
the project is going smoothly and better than originally anticipated. Planners
originally thought the topsoil would have to be replaced, but that was not the
case.
In May, a good portion of the month was spent
relocating trailers and redesigning the driveway to the North Shore Spirit
field. Donovan said the bulk of that work is now complete and went as planned.
Contractors are continuing to prepare the field
for the installation of the track and playing in field.
This is the first phase of the $11 million project
to redesign the former Manning Bowl, which stood on the site for 66 years before
it was demolished last year. The first phase is slated to cost close to $4
million.
Senate's Budget
Includes Money for New Manning Bowl
By James Haynes
Thursday, November 24, 2005
LYNN - Money
earmarked for the Manning Field has cleared a second procedural hurdle, with
members of the state Senate approving a supplementary budget that includes $5
million for the stadium.
State senators approved their version of the 2005 supplemental budget Tuesday
afternoon, including $5 million for the new Manning Field in a $12.1 million
Department of Housing and Community Development line item.
"I was able to convince my colleagues of the importance of the project and
got some more money into the senate version," said state Sen. Thomas McGee.
"I was very happy to get some success with this. It's very important for
the kids in our community. And the Senate has been working with our colleagues
in the House to see this through."
The Senate language more than doubles the amount set aside in the October copy
of the House's budget. In that version, local delegates were able to secure $2
million in direct funding for construction and $200,000 for brownfield cleanup -
which the city would use to remediate soil contamination on the site.
The supplementary budget goes to conference committee next, and any cash for
the facility must cross the desk of Gov. Mitt Romney without being vetoed. The
latter is a significant step, as Romney squashed $2 million set aside for the
66-year-old Manning Bowl in last year's supplementary budget.
City officials, however, greeted the Senate budget with cautious optimism.
"This is another big step in the financing process. The House has come
through and now the Senate has come through too. From here we will work with our
state legislators as it goes to conference committee and to the governor for his
signature," said James Marsh, chief of staff for Mayor Edward Clancy.
"Between the state, city and funding resources such as Urban Self Help
Grants and the National Football League we are all working together to make this
a reality."
$1M Trimmed off Manning Field
Project
By James Haynes, The Daily Item of Lynn, Wednesday,
November 16, 2005
LYNN - After months
of estimates, rough figures and best guesses, city officials have hard numbers
on the Manning Field project.
Members of the Manning Field Commission recommended pruning nearly a
million dollars worth of amenities from a $12.2 million design development
estimate presented by project architects last Thursday, in an attempt to shrink
the price tag back within the city's $11.3 million budget, said committee
chairman Deputy Police Chief Kevin Coppinger.
"We have an $11.3 million budget. That's what we told the mayor, it's what
we told the council. That's the number we are looking at to build this
project," Coppinger said. "There were things that the architects threw
at us that - I wouldn't call them luxury items - that were features not critical
to the project. We'll still be able to build what we believe is a first-class
facility."
Construction cost estimates, for both phases of the project, set the field and
track construction of phase one at approximately $3.8 million and subsequent
construction of the main building projected to cost $6.1 million.
The total estimate exceeds the budgeted construction cost of $9.1 million,
and additional expenses around the construction drove total cost to the $12.2
million mark.
Given the overrun, committee members examined potential reductions in earthwork,
utility, site lighting, landscaping, parking and site improvements, culling
approximately $918,000 from the total.
"The committee decided to defer all cost reductions presented to phase two
future work, except ornamental fencing, ornamental piers, retaining walls
concrete stair and walk at entrance and $50,000 of landscaping," read
minutes from the Nov. 10 committee meeting.
The itemized estimate may answer oft-repeated demands for solid numbers from
several city councilors -most notably Charles O'Brien. Coppinger said copies of
the document were issued to Mayor Edward Clancy's office and Inspectional
Services Chief Michael Donovan last week, and that copies will be forwarded to
the Council office this week.
"We promised (Councilor O'Brien) that we would return (when we had good
numbers), and we're still trying to tie up a few loose strings on this,"
Coppinger said. "There's still a lot of work to do, but we did promise the
councilor we'd get back to him and answer his questions."
Bidding on construction isn't expected to begin until after the New Year.
Although the committee is still crossing its collective fingers that exemptions
to state standards for washroom facilities will make the final version of this
fall's state supplementary budget, Coppinger said planners are going forward on
the presumptionthat "we own the toilets" - an estimated $600,000 cost
the city had hoped to avoid.
City officials are also looking to the State House this fall to see if $2
million for the project, included in the House version of the supplementary
budget, clears the governor's desk intact.
"We've got about $4.2 million in bond money, and we're still going after
grants," said James Marsh, Clancy's chief of staff. "We were
successful in capturing the Urban Self Help grant and recently made our pitch to
the NFL. Now we're waiting to see what happens at state level."